How Costs Roll Up from Budget to SOV to Draw

Construction costs begin in a detailed budget, are grouped into SOV line items for lender tracking, and are then used to determine draw eligibility based on verified percentage completion.

The construction budget tracks detailed cost categories such as labor, materials, permits, and subcontractor bids. These costs are often organized using standardized cost codes.

For lender purposes, those detailed categories are grouped into broader SOV line items that represent construction phases. The SOV becomes the tool used to approve draw requests.

When a draw is submitted, the bank verifies completion percentages against the SOV. Funds are released based on the approved allocation and verified progress.

Key facts

  • Budgets track detailed cost planning
  • SOVs group costs into construction phases
  • Draws are based on SOV percentages
  • Alignment prevents funding delays

What lenders look at

Banks focus on the SOV during draw administration because it reflects value progression. Misalignment between budget and SOV increases review time and risk.

Common mistakes

  • Allowing SOV totals to differ from budget totals
  • Completing work outside SOV sequencing
  • Ignoring budget overruns before draw submission
  • Failing to adjust SOV after approved changes

When this typically happens

  • During draw preparation
  • When costs exceed estimates
  • When sequencing changes occur

Frequently asked questions

Does the budget control draw payments?

No. The SOV controls draw approvals.

Should the SOV equal the contract total?

Yes. The SOV must match the total approved contract value.

Can misalignment delay funding?

Yes. Banks may pause draws until discrepancies are resolved.