How Banks Use the SOV During Draw Reviews
During draw reviews, banks compare completed work against the approved SOV to determine how much funding to release. The SOV serves as the reference for verifying percentage completion and payment eligibility.
When a draw request is submitted, the lender reviews inspection reports and compares progress to the corresponding SOV line items. Funding is typically released based on verified percentage completion.
If work completed does not align with the SOV structure, lenders may reduce or delay payment. Accuracy in SOV categories ensures smoother draw approvals.
The SOV acts as the scoring sheet the bank uses to evaluate each draw request.
Key facts
- Draw approvals are based on SOV percentages
- Inspections are compared against SOV lines
- Misalignment can delay funding
- SOV totals must remain consistent
What lenders look at
The SOV allows lenders to track value progression and prevent overpayment. It provides a standardized framework for inspection verification and fund control.
Common mistakes
- Requesting draws that exceed SOV allocation
- Completing work out of sequence without SOV adjustment
- Submitting inaccurate percentage completions
- Ignoring retainage calculations
When this typically happens
- At each draw submission
- After inspections are completed
- When project sequencing changes
Frequently asked questions
Can banks change SOV percentages?
They may require adjustments if progress does not match reported completion.
Is inspection required for every SOV line?
Not always, but inspections commonly verify major phases.
What happens if work is ahead of the SOV schedule?
The bank may limit payment to the approved SOV allocation.