How an SOV Is Different from Your Construction Budget
Your budget is the internal record of what every piece of the build costs. The schedule of values (SOV) is the billing breakdown the lender and inspector use to decide how much of each draw to release. The SOV is normally built from the budget by grouping its cost lines into a smaller set of billable stages, so the two should add up to the same total, but they are not the same document and they do different jobs.
Two documents, two jobs
A construction budget is for you. It tracks what you expect each item to cost and what you actually spend, usually organized by cost code (NAHB-style categories are common in residential work). It can be as detailed as you like, and on larger projects it can run to hundreds of cost codes.
A schedule of values is for the people paying out the money. It breaks the total contract or loan amount into the stages of work that will be billed against, so each draw can be checked line by line. Construction accounting guidance is blunt about the difference: the SOV is the external billing document, the budget is internal cost tracking, and mixing the two up is the most common mistake on this topic [1].
How the SOV is built from the budget
A well-built SOV rolls up cleanly from the budget: each SOV line covers a defined group of budget lines, and the totals match [1]. Here is an illustrative example for a $400,000 build:
| SOV line | Amount | Budget lines it contains |
|---|---|---|
| 1. Site work and permits | $28,000 | Permits and fees $5,500; clearing and grading $12,500; temporary utilities $3,000; erosion control $2,500; survey and staking $4,500 |
| 2. Foundation | $46,000 | Excavation $9,000; footings $12,000; foundation walls and slab $22,000; waterproofing $3,000 |
| 3. Framing and dried-in shell | $98,000 | Framing labor $32,000; lumber and trusses $40,000; windows and exterior doors $16,000; roofing $10,000 |
| 4. Mechanical, electrical, plumbing rough-ins | $62,000 | Plumbing rough $18,000; electrical rough $22,000; HVAC rough $22,000 |
| 5. Insulation and drywall | $34,000 | Insulation $9,000; drywall $25,000 |
| 6. Interior finishes | $88,000 | Cabinets and counters $32,000; flooring $18,000; paint $12,000; trim and interior doors $14,000; tile $12,000 |
| 7. Exterior finishes and site | $28,000 | Siding $14,000; driveway and flatwork $8,000; landscaping $6,000 |
| 8. Fixtures and closeout | $16,000 | Plumbing fixtures $6,000; electrical fixtures and devices $5,500; appliance allowance $3,000; final cleaning $1,500 |
| Total | $400,000 | Matches the budget total |
You track costs in the budget all the way down to the individual line. The people funding and inspecting the build only see the eight SOV lines.
How the SOV is used on every draw
For each draw you report how far along each SOV line is. The amount of the draw is the value of the work completed on each line, less anything already paid in earlier draws, and less retainage if some is held back. Example: if line 3 is $98,000 and the inspector agrees it is 60% complete, that is $58,800 of work. With 10% retainage, $5,880 is held back and $52,920 is payable.
On commercial and many residential jobs this is done on the AIA payment forms. The SOV loads line by line onto the G703 continuation sheet, and the G703 rolls up to the G702 cover form, which shows totals, retainage, prior payments, and the amount due this period [1][2]. Change orders are usually listed on their own rather than by rewriting the original SOV each time [2]. Plenty of funders use their own form instead, but the AIA layout is so widely copied that the structure is usually the same [3].
What gets checked on each draw
Whoever is funding the build generally wants three things behind each draw request: the request tied to the approved budget line by line with percent complete, an inspection, and a title update showing nothing new has been recorded against the property since the last draw [4]. The inspection is what confirms that each line or stage is as complete as the request says [5].
This only works if each line is valued at what it really costs. When line values match actual pricing, percent complete equals dollars earned, so the amount that can be funded follows directly from the inspection [6]. If early lines are inflated, the reviewer sees money going out faster than work is finished, which is the kind of mismatch the SOV exists to prevent.
Why you will see the terms used differently
The terms are not used consistently. Some owner-builder guidance treats the SOV as a line-item estimate summarized into a budget breakdown that then becomes your project budget [7]. Construction accounting sources keep the two documents separate [1]. The idea underneath is the same either way: a detailed record of costs on one side, and a shorter breakdown of the work that gets billed and paid on the other. Whatever your project calls them, keep the two totals equal and keep both up to date.
Sources
- Corpay, "Schedule of Values in Construction": https://www.corpay.com/en-CHI/resources/blog/schedule-of-values
- AIA, G703-1992 instructions: https://help.aiacontracts.com/hc/en-us/articles/1500009308302
- Autodesk Construction Cloud, "A Guide to G702 and G703 Forms in AIA Billing": https://www.autodesk.com/blogs/construction/g702-g703-forms-aia-billing/
- BiggerPockets, lender thread "what do you need to see before you release a draw?": https://www.biggerpockets.com/posts/7325433
- GetBuilt, "Construction lending basics: draw inspections": https://getbuilt.com/blog/construction-lending-basics-draw-inspections/
- Land Gorilla, "Why Did the Completion Percentage Go Down?": https://landgorilla.com/blog/why-did-the-completion-percentage-go-down/
- Building Advisor, "Draw Schedules": https://buildingadvisor.com/welcome-to-the-building-advisor/project-management/finance/draw-schedules/
Key facts
- The budget tracks estimated and actual costs and is for your internal control; the SOV is the billing breakdown used to release loan funds.
- SOV lines should each map to a defined group of budget lines, and the SOV total should equal the budget total.
- Each draw is calculated from percent complete on each SOV line, less earlier draws and any retainage.
- Draws are usually supported by an inspection, lien waivers, and a title update.
- Terminology and formats vary from project to project, but the structure is the same: a detailed cost record and a shorter billing breakdown with matching totals.
What lenders look at
Whoever releases the money uses the SOV (or the approved budget treated as one) as the reference for inspections and funding. In general they want a draw request tied to the approved budget line by line with percent complete, an inspection that confirms it, and paperwork showing the work is paid for and free of liens [4][5]. Specific requirements differ from one lender to the next, so this describes the general pattern, not a universal rule.
Common mistakes
- Treating the SOV as a duplicate of the budget, then building it separately so the totals drift apart.
- Making the SOV so detailed it is just a copy of a 200-line budget, or so lumpy that one line holds a third of the loan.
- Front-loading, meaning inflating early lines so more money is released sooner than the work justifies.
- Updating the budget after a cost change but not the SOV, or the reverse.
- Rewriting the SOV for every change order instead of listing change orders separately [2].
- Using a template without checking that its structure fits how your project will actually be billed.
When this typically happens
- During loan setup, when the budget and draw schedule are reviewed.
- At the first draw, when the SOV becomes the form you bill against.
- Whenever a change order, allowance overage, or cost overrun changes a line's value.
- At final draw, when every SOV line should reach 100 percent and retainage is released.
Frequently asked questions
Can my SOV match my budget exactly?
For a small residential build it sometimes can. As projects get larger or more formal, the SOV is usually a shorter, stage-based breakdown that groups budget lines, so the two documents differ in detail but match in total [1][7].
Which document controls how much money I get?
In most draw processes, the SOV (or whatever breakdown was approved at the start) controls the draw, because each request is checked against it line by line [4].
Do I need AIA forms?
Not necessarily. Many funders have their own draw form. The AIA G702 and G703 are the widely recognized standard, and their format is often used even where the document does not carry the AIA label [3].
What happens if costs change after the SOV is approved?
Keep the budget current as costs change. For changes in scope or price, use a change order and list it separately from the original SOV lines rather than reworking the SOV [2].
Who checks that a line is really complete?
Usually an inspector or third-party reviewer, who confirms the percent complete on each line before funds are released [5].