Change Orders Explained in Residential Construction
A change order is a written agreement that modifies the original construction contract by adding, deleting, or changing the scope of work, the price, or the timeline. A complete one states what is changing, what it costs, and how much time it adds, and is signed before the changed work starts.
What a change order is
A change order is a written agreement that modifies the original construction contract. It may add, delete, or change the scope of work, price, or timeline because of unforeseen circumstances, design adjustments, or the owner's wishes [1]. Change orders are a routine part of construction, and they are formal amendments to the contract [2].
What it should include
A completed change order specifies the type of change, the scope and cost of the new work, and the additional time added to the schedule [3]. Language should be as specific as possible about the description, cost, duration, and payment [4]. A well-written one gives both sides a record of what changed, what it cost, and who pays [4]. It also helps to show the running total: the original contract value, the value of all past approved change orders, and the cost of the current one [5].
Get it in writing first
Many contracts say there can be no oral modification and that only signed, written change orders are binding. The usual process is that owner and contractor agree on scope, price, and schedule, a written change order is prepared and signed by all parties, and only then does the changed work proceed. In practice, contractors often proceed with extra work without a written change order, and that is where disputes start [6]. Working without approval increases liability and the risk of non-payment [5]. If everyone who signed the main contract is a party to it, all of them should sign the change order too [4].
Types you will see
- Additive. Changes that increase the cost of the project [7].
- Deductive or no-cost. The total value of a change order can be positive, negative, or neutral, and a no-dollar change order covers a scope change done for no added cost and no credit [8].
- Clarification. These do not change the budget but become part of the written history of the job, and they help clients get used to the process [9].
Not every change requires a change order [7].
What it can cost
Contractors often build a change order markup into the contract up front. One source puts the average at about 10 to 15 percent for overhead and profit [10]. Another contractor describes charging administration time, materials, crew time, subcontractor cost, and full profit [9]. Read your contract before you ask for a change, so the price does not come as a surprise.
Effect on the schedule
Change orders can add time because of the additional work, waiting for new materials or inspections, and review and approval time [1].
Sources
- Georgia Department of Community Affairs, "Change order FAQs": https://dca.georgia.gov/node/22926
- NetSuite, "Change order": https://www.netsuite.com/portal/resource/articles/accounting/change-order.shtml
- Fine Homebuilding / JLC, "Getting change orders under control": https://www.jlconline.com/business/getting-change-orders-under-control_o/
- Fine Homebuilding, "Change orders can help avoid dreaded lawsuits": https://www.finehomebuilding.com/how-to/departments/commentary/change-orders-can-help-avoid-dreaded-lawsuits.aspx
- Procore, "How construction change orders work": https://www.procore.com/library/how-construction-change-orders-work
- American Bar Association, "Construction 101: basics of change orders": https://www.americanbar.org/groups/construction_industry/resources/under-construction/archive/construction-101-basics-change-orders/
- Hunker, "What is a construction change order?": https://www.hunker.com/13768603/what-is-a-construction-change-order/
- CUNY City Tech, "Change orders": https://openlab.citytech.cuny.edu/cm2/?p=58
- JLC, "Getting change orders under control" (full article): https://www.jlconline.com//business/getting-change-orders-under-control_o/
- Autodesk, "What is a construction change order?": https://www.autodesk.com/blogs/construction/change-orders/
Key facts
- A change order is a written agreement that modifies the contract's scope, price, or schedule.
- It should state what changes, what it costs, and how much time it adds.
- Get it signed before the changed work starts, not after.
- Change orders can add cost, reduce cost, or be cost-neutral.
- Contracts often include a markup on change order work; read it before you ask for a change.
What lenders look at
A change that raises the total cost or moves the schedule affects the budget a lender approved. A signed change order is the record that shows what changed and why, which is what a reviewer looks for before it will match later draw requests to the budget. How a lender treats the added cost, such as whether it can be financed or must come from your own funds, depends on the loan terms.
Common mistakes
- Agreeing to a change verbally and papering it later.
- Starting changed work before the change order is signed.
- Not asking what the change does to the schedule.
- Forgetting that the contract may add a markup to change order work.
- Not keeping a running total of approved changes against the original contract.
When this typically happens
- When you change a design or selection after work has started.
- When site conditions or inspections force an unplanned change.
- Before each draw, when approved changes need to be reflected in the budget.
Frequently asked questions
Does every change need a change order?
No. Not every change requires one, but any change to scope, price, or schedule should be documented in writing [7][2].
Is a verbal agreement enough?
Often not. Many contracts say only signed, written change orders are binding, and contractors who proceed without one risk disputes and non-payment [5][6].
How much extra will a change order cost?
It depends on your contract. One source puts a typical markup for overhead and profit at 10 to 15 percent [10].
Can a change order save money?
Yes. A change order can be positive, negative, or neutral in value [8].