NAHB Cost Code to SOV Mapping Guide
NAHB cost codes organize detailed construction expenses, while a Schedule of Values (SOV) groups those costs into broader construction phases for lender draw tracking. Mapping NAHB codes correctly into SOV line items ensures budgets, inspections, and draw approvals remain aligned.
NAHB cost codes are highly detailed and used primarily for budgeting and internal cost tracking. They break construction into granular categories such as excavation, concrete, framing labor, roofing materials, and finish carpentry.
Lenders, however, administer draws using broader SOV categories that reflect value progression. These SOV categories typically align with major construction phases rather than individual trade-level costs.
Mapping means grouping related NAHB cost codes under the appropriate SOV phase. When done correctly, this prevents mismatches between budget totals and SOV allocations during draw reviews.
Key facts
- NAHB codes are detailed cost categories
- SOV line items represent construction phases
- Multiple NAHB codes typically roll into one SOV line
- Proper mapping prevents draw discrepancies
What lenders look at
Banks do not evaluate draw payments using detailed cost codes. They evaluate percentage completion by SOV phase. Clear mapping ensures loan funds are released based on verified progress without confusion.
Common mistakes
- Attempting to use NAHB codes directly as SOV lines
- Over-fragmenting the SOV with too many categories
- Allowing SOV totals to differ from budget totals
- Failing to update mapping after approved budget changes
When this typically happens
- During SOV creation
- During loan underwriting
- When preparing the first draw request
Frequently asked questions
Can NAHB cost codes be used directly as SOV line items?
Usually no. Banks prefer broader phase-based SOV groupings.
Should SOV totals equal the total budget?
Yes. The SOV must match the approved contract or loan amount.
Can incorrect mapping delay draws?
Yes. Misalignment between cost codes and SOV phases often causes funding delays.