How Long Do Building Permits Really Take?

There is no national timeline. Published targets for new residential plan review range from under a day to several weeks in different jurisdictions, and some places report many months for a single-family home once resubmittals and other approvals are included. Plan for your own building department's real numbers, not a typical one.

The range is wide

These are published figures from different building departments. They illustrate how much the answer varies, not what yours will be.

Jurisdiction (type)Published figure
Bend, OregonResidential plan reviews typically take less than a day [1]
Fort Worth, TexasFirst review comments within 7 business days for residential [2]
Centennial, Colorado10 to 15 business days for new residential, counted after the plan review fee is paid [3]
Pleasantville, New YorkAbout three weeks for plan review of a new residential dwelling [4]
Clark County, NevadaA 21-day first-review goal for a custom single-family residence [5]
Lynnwood, Washington4 to 8 weeks for new residential review, with 1 to 2 weeks of permit center processing in addition [6]
Mammoth Lakes, CaliforniaA new single-family residence can take from 6 months to more than a year to get through plan review [7]

Note that many of these are targets for the first review, not the time to a finished permit.

What stretches the timeline

  • Resubmittals. Reviews often come back with comments. One California town reports that initial plan review takes 10 to 14 business days and each later review typically 5 to 7, and that failing to address specific comments significantly delays the process [7]. Another notes that missing or non-compliant information creates a back-and-forth [8].
  • Other approvals first. In one Virginia city, the building permit cannot be issued until the grading plan or site plan is approved, so the building permit can sit with staff for a long time [9].
  • Outside reviewers. One county's published review numbers count only the building reviewers and do not include the time outside reviewers take [10].
  • Public notice. In some places, a required public notice and comment period can lengthen the review [11].

Planning around it

Start the permit process before you need it, because a lender generally wants permits in place: published lender checklists list the building permit among the required construction documents [12]. Submit complete plans, answer every comment fully, and find out which other approvals, such as grading, site plan, septic, or zoning, must come first. Ask your building department for its current turnaround and recent actual times.

Sources

  1. City of Bend, "Building Safety Division review times": https://bendoregon.gov/news/building-safety-division-review-times/
  2. City of Fort Worth, "Review timeframes": https://www.fortworthtexas.gov/departments/development-services/permits/review-timeframes
  3. City of Centennial, "Building permit review schedule": https://www.centennialco.gov/Government/Departments/Building/Building-Review-Schedule
  4. Village of Pleasantville, "How long do I have to wait to obtain a permit?": https://www.pleasantville-ny.gov/node/493
  5. Clark County, NV, "Plan review timelines": https://clarkcountynv.gov/government/departments/building___fire_prevention/plan_review/plan_review_timelines.php
  6. City of Lynnwood, "Permit center review times": https://lynnwoodwa.gov/files/sharedassets/public/v/1/dbs/permit-applications-amp-forms/permit-center-review-times-2024.10.23.pdf
  7. Town of Mammoth Lakes, "How long does it take?": https://townofmammothlakes.ca.gov/FAQ.aspx?QID=73
  8. City of Walnut Creek, "Turnaround times": https://www.walnutcreekca.gov/government/community-development-department/permits/turnaround-times
  9. City of Fairfax, "Permit review metrics": https://www.fairfaxva.gov/Property-Business/Permit-License-Hub/Permit-Review-Metrics
  10. Fairfax County, "Land development metrics": https://www.fairfaxcounty.gov/plan2build/development-review-metrics
  11. City of Mercer Island, "Review timelines": https://mercerisland.gov/node/11101
  12. Live Oak Bank, "Construction loan checklist": https://resources.liveoak.bank/hubfs/construction-loans/Loan-Checklist.pdf

Key facts

  • There is no national permit timeline; published residential review targets range from under a day to many weeks.
  • Some jurisdictions report many months for a new single-family home once resubmittals are counted.
  • Resubmittals after review comments are a leading cause of delay.
  • Grading, site plan, or other approvals may have to be completed before the building permit can issue.
  • Lenders generally want the permit in hand, so permit time can affect your closing and start dates.

What lenders look at

Whoever is lending generally wants permits issued, or at least a clear path to them, before it commits to funding. A slow permit can therefore delay closing and the first draw. Plan your schedule and your interest costs around real local turnaround times, not a best case.

Common mistakes

  • Using a published first-review target as the total time to a permit.
  • Submitting incomplete plans and then waiting through repeated review cycles.
  • Not finding out which approvals, such as grading or zoning, must come first.
  • Scheduling subcontractors and deliveries before the permit is issued.
  • Not budgeting interest and carrying costs for a longer-than-expected approval.

When this typically happens

  • Before closing, since lenders commonly want permits in place.
  • In review rounds: first review, comments, and resubmittal.
  • Before any work starts on site.

Frequently asked questions

How long should I plan for a residential permit?

Ask your local building department. Published figures range from under a day to several weeks for plan review, and some jurisdictions report many months for a new house [1][4][7].

What slows a permit down most?

Resubmittals after review comments, plus other approvals that must come first, such as grading or site plans [7][9].

Do I need the permit before I close on my loan?

Lenders commonly want it, and published lender checklists list the building permit [12]. Ask your lender about timing.

Can I speed up review?

Submit complete plans, answer every comment fully, and confirm what other approvals you need. Some departments offer express routing for qualifying residential projects [11].