Retainage Explained (5–10% Holdbacks)
Retainage (also called retention or a holdback) is a percentage of each construction payment that is held back until the work is finished. It is usually 5 to 10 percent and is released near the end of the job, after final inspections, any punch-list work, and final lien waivers. It exists to give the payer leverage to make sure the work is completed properly.
What retainage is
Retainage is the withholding of part of a payment for a defined period to assure that a contractor or subcontractor finishes the work completely and correctly [1]. It is also called retention or a holdback [2]. The held amount gives the owner something concrete to apply if the contractor does not deliver, without having to chase a refund after the money is already gone [3].
On a typical project, a fixed percentage, usually 5 to 10 percent, is withheld from each payment application and held in reserve until the work is substantially complete [4].
How it is calculated
Retainage is a percentage of the amount billed on each payment, and the held amount builds up into a running balance that is released at defined milestones near the end [3].
Here is an illustrative example with 10 percent retainage:
| Amount | |
|---|---|
| Work approved for this draw | $60,000 |
| Retainage held (10%) | $6,000 |
| Paid out now | $54,000 |
If the whole $400,000 project were billed this way, $40,000 would build up in retainage and would be released at the end. These figures are for illustration only.
When it is released
There is no fixed date. Release is tied to milestones, most commonly final completion and punch-list closeout, and sometimes a final inspection or certificate of occupancy [4]. Release typically starts at substantial completion and finishes once the punch list, final inspections, and lien waivers are cleared [5]. On projects that have a lender, the lender may add its own release conditions, including an independent inspection [2].
Some contracts include a retainage reduction clause that lowers the percentage once the project reaches a threshold, often around 50 percent complete, for example from 10 percent down to 5 percent [6]. If your contract has this language, it is worth tracking.
What controls the details
The contract sets the percentage, how it is calculated, the release milestone, and the documents required for release. A vague retainage clause is where billing disputes usually begin [5]. Rules also differ by state: some states cap the percentage or set release deadlines [7]. A general contractor may also hold the same percentage back from subcontractor payments and release it only after being paid by the owner [5].
Sources
- NetSuite, "Retainage": https://us-approval.netsuite.com/portal/resource/articles/accounting/retainage.shtml
- Built (GetBuilt), "What is retainage in construction": https://getbuilt.com/blog/what-is-retainage-in-construction/
- Corpay, "Construction Retainage Explained": https://www.corpay.com/en-GB/resources/blog/construction-retainage
- Ramp, "Construction retainage": https://ramp.com/blog/construction-retainage
- Quickbase, "What is retainage": https://www.quickbase.com/blog/what-is-retainage
- Corpay, "Construction Retainage Explained" (rate step-downs): https://www.corpay.com/it/resources/blog/construction-retainage
- Corpay, "Construction Retainage Explained" (state differences): https://www.corpay.com/fr-CA/resources/blog/construction-retainage
Key facts
- Retainage is a percentage of each payment that is held back until the work is complete.
- A fixed holdback of roughly 5 to 10 percent is common, but the contract or loan terms set the actual number.
- It is released at defined milestones near the end, such as final completion, punch-list closeout, final inspection, and final lien waivers.
- Some agreements reduce the percentage once the project passes a threshold, often around 50 percent complete.
- Retainage rules, including caps and release deadlines, differ by state.
What lenders look at
Holding back part of every payment keeps some leverage in place until the finish line. For whoever is releasing money, it protects against unfinished or defective work and unresolved claims. They typically want the holdback released only once final inspections, any punch-list work, and final lien waivers are complete. Whether retainage applies at all, and at what percentage, depends on the loan or contract terms.
Common mistakes
- Leaving retainage out of cash flow planning, so the last 5 to 10 percent is not there when expected.
- Expecting retainage to be released early, before punch-list items and final paperwork are done.
- Paying a contractor in full and losing the leverage the holdback was meant to provide.
- Not reading the retainage terms in the contract or loan documents.
- Holding retainage from one party but not applying the same terms to the others, which can create disputes.
When this typically happens
- On every draw or payment application throughout the build.
- As a running balance that grows until substantial completion.
- At release, after final inspection, punch-list completion, and final lien waivers.
Frequently asked questions
Is retainage required on every construction project?
No. It depends on the contract or loan terms, and in some places on state law. Where it applies, 5 to 10 percent is a common range [4][7].
When is retainage usually released?
Typically after substantial completion, once the punch list, final inspections, and lien waivers are cleared. The exact trigger is set in the contract [5].
Can retainage be negotiated?
It can be, since the percentage and release terms are set in the contract. Some agreements step the rate down at a completion milestone such as 50 percent [6].
Do retainage rules differ by state?
Yes. Caps and release rules vary sharply by state, so check the rules where the project is located [7].