Construction Timeline Expectations
How long each phase typically takes, common delays, and how to track against your timeline.
Average Build Timeline
A typical custom home takes 12-18 months to build. Owner-builders average 15.1 months due to the learning curve and coordination challenges.
Phase Duration Estimates
| Phase | Typical Duration |
|---|---|
| Pre-Construction | 2-4 weeks |
| Foundation | 2-4 weeks |
| Framing | 4-8 weeks |
| MEP Rough-In | 3-6 weeks |
| Insulation & Drywall | 3-5 weeks |
| Exterior | 4-8 weeks |
| Interior Finishes | 6-12 weeks |
| Final | 2-4 weeks |
Common Delays
- Weather — Rain, extreme cold, and wind can halt work for days or weeks
- Material delays — Order specialty items (windows, cabinets, appliances) early
- Inspection wait times — Budget 1-2 weeks for each inspection
- Subcontractor scheduling — Good subs are busy; book them months in advance
TIP: Add 20-30% buffer to every phase estimate. This is realistic, not pessimistic.