What a Certificate of Occupancy Means
A certificate of occupancy (CO) is an official document from the local government certifying that a building is safe, code-compliant, and approved to be occupied. It is issued after the building passes its final inspection, and in most places a new home cannot legally be occupied without it.
What it is
A certificate of occupancy is an official document from the local government certifying that a building is safe, code-compliant, and approved for its intended use, and it is required before legal occupancy [1]. Procedures and requirements vary widely from one jurisdiction to another [2]. In general, one is required when a new building is constructed [2].
How you get one
A CO is issued at the end of construction, after the local building inspector conducts a final inspection [1]. The building must pass all the on-site inspections, such as mechanical and plumbing, plus a final inspection. In some places you must request the final inspection yourself when the building is ready [3].
What the final inspection checks varies by place. One county's example: the final inspection comes after finish grading, with the building complete, plumbing fixtures set, heating equipment working, and final electrical signed off [4]. Another city lists the minimum requirements as a building final, a site final, a zoning inspection when required, and approved as-built drawings for new construction [5]. Check your own building department's list.
If the property fails, you correct the deficiencies and schedule a re-inspection before the certificate will be issued [1].
Timing
Do not assume it arrives the same day. One Georgia county issues COs approximately 24 to 48 hours after the final inspection and states that none are issued the same day [6]. A Colorado county says the certificate attaches to the permit within 48 hours of final inspection approval [4].
Temporary certificates
Some jurisdictions issue a temporary certificate of occupancy (TCO) when the building is safe to occupy but some work is not finished. A TCO normally has an expiration date and a list of conditions that must be met before the final certificate is issued [7].
Why it matters beyond moving in
- Legal occupancy. In one county, no new home may be occupied before the building official issues a CO [6].
- Lenders and title. Lenders and title companies for new-construction closings often expect evidence of final approval [7].
- Selling. A CO is generally part of selling a newly built home, and the process and cost of getting one vary by location [8].
Sources
- LegalZoom, "Certificate of occupancy": https://www.legalzoom.com/business-glossary/certificate-of-occupancy
- Wikipedia, "Certificate of occupancy": https://Www.Wikipedia.org/wiki/Certificate_of_occupancy
- City of Minneapolis, "Certificate of occupancy": https://www.minneapolismn.gov/business-services/licenses-permits-inspections/construction-permits/building-safety/certificate-of-occupancy/
- Larimer County, "Certificate of occupancy": https://www.larimer.gov/building/certificate-occupancy
- City of Sandy Springs, "Certificate of occupancy": https://www.sandyspringsga.gov/certificate-occupancy/
- Banks County, GA, "Certificate of occupancy": https://www.bankscountyga.org/building-inspections/page/certificate-occupancy
- InspectAndTest, "Certificate of occupancy": https://inspectandtest.net/guides/certificate-of-occupancy/
- Bankrate, "Certificate of occupancy": https://www.bankrate.com/real-estate/certificate-of-occupancy
Key facts
- A certificate of occupancy certifies that a building is safe, code-compliant, and approved to be occupied.
- It is issued after the building passes its final inspection.
- Requirements and timing vary widely by jurisdiction.
- A temporary certificate may be issued with conditions and an expiration date.
- Lenders and title companies for new-construction closings often expect evidence of final approval.
What lenders look at
For a lender, the certificate of occupancy is evidence that the house is finished to code and can be lived in, which is the condition for closing out a construction loan or converting it to permanent financing. Lenders and title companies for new-construction closings often expect evidence of final approval. Exact requirements vary by lender.
Common mistakes
- Moving in before the CO is issued.
- Waiting to request the final inspection until the day you want to move in.
- Leaving grading, fixtures, or other items incomplete before the final inspection.
- Accepting a temporary CO without knowing its conditions and expiration.
- Not keeping the approved as-built drawings if your jurisdiction requires them.
When this typically happens
- At the end of construction, after all trade inspections pass.
- Before move-in and before the loan closes out or converts.
- Again if the building's use or occupancy classification changes.
Frequently asked questions
Can I move in before I have the CO?
In most places, no. One county states that no new home may be occupied before the building official issues one [6].
How long does it take to get the CO after the final inspection?
It varies. Examples include 24 to 48 hours, and within 48 hours [4][6].
What if I fail the final inspection?
You correct the problems and schedule a re-inspection before the certificate is issued [1].
What is a temporary certificate of occupancy?
A TCO allows occupancy while some work is unfinished. It normally has an expiration date and conditions to meet before the final certificate [7].
How OwnerDraw helps