How to Budget Contingency Correctly

Contingency is money set aside in the budget for costs you cannot predict. A common approach is a percentage of the construction cost: published guides cite 5 to 7 percent for a new build with complete plans and a known site, and up to 10 or 15 percent when more is uncertain. The riskier or less defined the project, the more contingency it needs.

What contingency is

In residential construction, a contingency is a percentage or fixed amount of money set aside to cover unanticipated costs that arise during a project [1]. The American Institute of Architects describes it as the amount or percentage included in the project budget to cover unpredictable changes in the work [2].

It is not the same as an allowance. An allowance is a placeholder for something you know you need but have not selected yet. Contingency is for things you cannot yet predict, such as unforeseen site conditions or errors.

How much to set aside

There is no single number that works for every job. The right percentage depends on how much risk the project carries [3].

SourceRange reported
Builder software guide5 to 10 percent of the total project budget, depending on complexity, location, and risk [1]
Cost guide for new residential construction5 to 7 percent for complete plans and a known site [3][4]
Design firm5 to 15 percent of the contracted project cost [5]

A clean lot with complete drawings and a finished design needs a smaller reserve than a project with unfinalized plans, unknown soil conditions, or a complex site [4].

How to calculate it

The basic formula is the estimated project cost multiplied by the contingency percentage [1]. For example, on a $400,000 construction budget:

PercentageContingency
5%$20,000
7%$28,000
10%$40,000

The percentages are illustrations, not recommendations for your project. Choose yours based on how complete your plans are, what you know about the site, and how much of the work is still unpriced.

Lenders and contingency

Some construction lenders require a certain amount of cash set aside in case building costs end up higher than expected [6]. Ask whether yours does, and whether contingency is included in the loan amount or has to come from your own funds.

Managing it

Record contingency as its own budget line, and track every use of it. If you spend part of it on a cost overrun, the remaining balance is what is left to cover the rest of the build. Reassess your strategy periodically to reflect new risks, so the budget stays realistic [1].

Sources

  1. Buildertrend, "Construction contingency guide for residential builders": https://buildertrend.com/blog/construction-contingency/
  2. AIA, "Managing the contingency allowance": https://www.aia.org/best-practices/6401741-managing-the-contingency-allowance
  3. Projul, "Construction contingency budget guide": https://projul.com/blog/construction-contingency-budget-guide
  4. Cost to Build House, "Construction contingency budget": https://www.costtobuildhouse.com/construction-contingency-budget
  5. Case Design, "Do I need a contingency budget?": https://www.casedesign.com/inspiration/do-i-need-a-contingency-budget-for-my-residential-construction-project/
  6. Quicken Loans, "What is a construction loan and how does it work?": https://www.quickenloans.com/learn/construction-loan

Key facts

  • Contingency is money set aside for costs that cannot be predicted when the budget is made.
  • Published ranges run from about 5 to 15 percent, with 5 to 7 percent cited for new builds with complete plans.
  • Less complete plans, unknown soil, and complex sites call for a higher percentage.
  • Contingency is different from an allowance, which covers known items not yet selected.
  • Some lenders require extra cash on hand in case costs come in higher than expected.

What lenders look at

A budget with no cushion looks unrealistic to a lender, because construction costs nearly always move. Contingency shows that you have planned for surprises. Some lenders require borrowers to hold extra cash in reserve, and whether contingency is financed or has to be paid from your own funds depends on the loan terms.

Common mistakes

  • Leaving contingency out to make the total look smaller.
  • Using a percentage from a generic rule instead of one matched to your plans and site.
  • Spending contingency on upgrades instead of unexpected costs.
  • Not tracking what has been used, so no one knows what is left.
  • Confusing contingency with allowances and counting them as the same cushion.

When this typically happens

  • When you build the initial budget, before loan approval.
  • As unexpected costs come up during construction.
  • When the budget is reviewed after major milestones.

Frequently asked questions

How much contingency should I include?

It depends on risk. Published guides cite 5 to 10 percent generally, 5 to 7 percent for new residential construction with complete plans and a known site, and 5 to 15 percent in other guides [1][3][5].

What is the difference between contingency and an allowance?

An allowance covers a known item that is not yet selected. Contingency covers costs that cannot be predicted.

Can I use contingency for upgrades?

It is meant for unforeseen costs. Using it for upgrades leaves nothing for real surprises.

Does my lender require contingency?

Some lenders want cash set aside for higher-than-expected costs [6]. Ask yours how it treats contingency.